Reconstruction of the state regional road P109 Kandava – Saldus, section 14.033 – 28.637 km
Client
VSIA “Latvijas Valsts ceļi”
Completion year
2024
Total amount
€6 276 742
Project description
The total length of the project is 14.604 km.
The project includes the removal of asphalt pavement, construction of culverts and drainage pipes, slope stabilization, and asphalt paving works.
Construction of 102237 m² of hot asphalt wearing course.
Electrical supply and external networks.
The project includes the removal of asphalt pavement, construction of culverts and drainage pipes, slope stabilization, and asphalt paving works.
Construction of 102237 m² of hot asphalt wearing course.
Electrical supply and external networks.
Other projects
Reconstruction of Highway V-22 (Bašēni – Mežgaļi) in Mārupe
Year: 2024
Construction of the area at the Zemgale Regional Waste Landfill “Brakšķi”, stages 1 and 2
Year: 2024
Reconstruction of Aizsargu Street in Jelgava
Year: 2024
Construction of a pedestrian and cyclist path along the state regional road P93 Jelgava – Iecava on the section from 3.20 km to 6.50 km (from Jelgava to the villages of Āne and Tetele)
Year: 2024